Subject: list of improvements 

From: Omar Pulido 

Date: 03/09/2017 03:18 PM 

To: lhughes@gatewaytola.org 

CC: Lisa Trifiletti <lisa@trifiletticonsulting.com> 


Laurie - per our convo this morning, please see list below of what we 
have down for the BID'S list of improvements. Do you think there is any 
chance we can get the cost estimates by next Tuesday? I know it's a 
quick turnaround and apologize. If not feasible, please let me know so I 
can try to help. 


* Plant new landscaping in the center median along Century 
Boulevard between Sepulveda Boulevard and La Cienega Boulevard 

* Install new Gateway to LA signage in the landscaped median along 
Century Boulevard 

* Install new pedestrian lighting along Century Boulevard proposed 
in the Century Corridor Streetscape Plan 

* Remove the existing landscaped parkways and replace with interim 
gravel improvements along Century Boulevard until the Century Corridor 
Streetscape Plan is implemented 

* Install new overhead LED Caltrans sign on Century Boulevard just 
east of Aviation Boulevard 

* Make improvements to Sepulveda tunnel included but not limited 
to, new paint along the tunnel walls and on-going maintenance 


Omar Pulido 

909-973-4794 <tel : (909 ) %20973 -4794>